September 2019
September is usually a hive of activity as the crew prepare
the vessel for what some of us consider to be the highlight of the steaming calendar
– The Leigh Arms Steam Party at Acton Bridge. Sadly the ongoing boiler tube
project meant it was a no-show for the Kerne, but that didn’t mean the month
could pass idly by.
A slight improvement in the weather enabled the deck team to
do a little more painting on deck. The new coat of buff paint to the sides of
the boiler casing has been enhanced with the black edging now applied which really
does smarten up the old girl’s appearance. Some further deck painting could be
the last this year which should see us through to the spring. The forward hatch
has been temporarily replaced with a piece of marine plywood whilst the former
has taken up residence in the Mate’s garage for stripping, staining and
re-varnishing which will enhance our newly restored Captain’s Cabin. A further enhancement to the cabin has been
the acquisition of a 1914 Eli Griffiths Wardroom oil lamp. When built, Kerne
relied on oil lighting as there was no electrical power aboard, and this
remained the case until the 1960’s when a small generator was installed. Sadly,
none of the original oil lamps survived, so now, polished and refurbished, the
Griffiths lamp adds a real period feel to the Cabin.
Work in the Wheelhouse is moving along; the replacement
trims to the drop-down windows have been manufactured and await fitting, and
various jobs such as the rigging of the whistle pull wire, hooks, brackets and
the restoration of the wheelhouse mounted lifebelt brackets have been carried
out. One major job is the installation of the wooden wheelhouse deck. The height
of this is critical, so that there is an air-gap, that the ships’ wheel does
not foul the deck, nor should the floor be to low so that the helmsman’s foot
can be trapped beneath the wheel. The deck also has to be capable of easy
removal so we can clean and paint the top of the boiler casing periodically. We
propose to install an angle iron frame onto which the decking will sit, but in
order to calculate the correct height of the frame it was necessary to refit
the ship’s wheel and Engine Room voice pipe. To fit the voice pipe we also had
to refit the compass and supporting shelf. This work had the additional benefit
of returning the Wheelhouse to something like its working appearance rather
than as a storage shed!
Down below in the Boiler Room, the tube project continues.
The somewhat laborious process has now been speeded up by the completion of a
new bit of ‘kit’, namely a hydraulic drive which is attached to the tap as it
re-cuts the treads in the tubeplates. This takes a lot of effort out of the
job, which we had been performed using hand operated ratchet gear. This will
now hopefully speed things up and we can move on to treading the tubes.
For the last 6 years or so, we have shared our quay with the
mv Altea II, an HM Border Force Rummage Training Vessel. She has been sold for re-commissioning
into commercial service in Rotterdam, leaving under tow by the tug MTS
Viscount. This marked the end of an era for Rummage Crew Training as facilities
have now been moved ashore.
Comments
Post a Comment