September 2018
September is usually a month of high activity and
anticipation for the annual Leigh Arms Steam Party at Acton Bridge. Well, at
least we had activity but the usual anticipation was sadly missing as we were
unable to attend the event with the tug owing to the ongoing boiler work.
On this particular subject, work is progressing slowly but
steadily, with some twenty tubes having now been carefully removed. It is hoped
that the remaining tubes will be out by the end of October, but delays have the
habit of thwarting the best of intentions!
As ever, there is always a rolling program of maintenance
work that we have to keep pace with so the needle guns and de-scalers have been
out with the after deck beneath the rope grating being the focus of attention,
as has the aft peak tank which has been scaled and cement-washed. Strangely
enough, this is not a job that is bristling with volunteers, in fact it is odd
how we seem to find other important jobs to do, but to be fair, Mate Paul doesn’t
shirk the challenge and once again tackled the job head on. The real trick is once
out of the aft peak tank is to get the overalls off quickly before you ‘set’.
As previously reported, the wheelhouse, which was re-built
in 1977 from the 1950’s structure, has seen better days. We have been awarded a
grant from the Pilgrim Trust to repair the structure, and Moorside Joinery have
taken on the task of re-creating the structure using as much of the original as
possible. The guys have been provided with a set of drawings of the original
that were drawn in 1976 and we now have a plan of action to move the job
forward. Firstly, we need to carefully strip out the existing wheelhouse and
store the equipment therein, together with the re-usable elements of the
structure. The slight stumbling block is that since our return from Cammell
Lairds following the hull repairs, our storage container has become something
of a dumping ground for all manner of bits and pieces – some useful and some
not so useful. The decision was taken to erect additional shelving down one
side of the container, but due to the clutter, there wasn’t room to install it.
A co-ordinated ‘attack’ was needed. On the agreed date a good number of
volunteers arrived, with the Chief Engineer appointed as the sole arbiter of
what would stay and what would go. So, as items were removed from the
container, the Chief would shout ‘Keep’, ‘Scrap’ or ‘Dump’. Despite there was
no mechanism for appeal the exercise without any violence and if a strong case
was proffered, it was a case of ‘Well you take it home then’. That seemed to
concentrate the mind. The following week, the shelving was duly installed, and
stowing of the kept items carried out.
A very worthwhile job well done, but we would all really
have preferred to have been preparing Kerne for a trip to Acton Bridge!
Comments
Post a Comment